The submarine cable segments of our network were laid by seven cable ships between July 1999 and January 2001. The oceanic laying of each segment of the network follows three main phases:
1. Cable Landings
The marine operation begins with the landing of the cable from a cable ship. The cable is generally floated ashore, suspended by buoys to avoid damage on the ocean floor. Once the cable is secured, the buoys are removed so that the cable can settle on the ocean floor. Alternatively, the cable is winched ashore through a conduit (typically around 1km in length) or bore-drilled from the shore.
This process is repeated at the other end of the segment, where the cable end is sealed and buoyed-off ready for pick-up by the cable ship following trans-oceanic laying.
2. Trans-Oceanic Laying
The cable ship follows a pre-determined route (the result of a detailed ocean-floor survey). The cable is either buried by plough-burial simultaneously with laying or surface-laid as required (the Southern Cross cable is buried in depths of less than 2000m wherever feasible). As cable ploughs cannot operate below about 1500m water depth, post-lay jet burial using ROVs was done from the end of cable ploughing down to water depths of 2000m. Adjustments to the cable slack and ship position are used to ensure that the cable rests on the ocean floor.
3. Final Splice
 |
 |
|
Beach Landing:
Takapuna, Auckland
5 September 1999
|
Conduit landing:
Clovelly, Sydney
8 July 1999
|
Upon arrival at the other end of the segment, the previously installed end is recovered aboard and the position of the cable ship taken. A final splice is then made and the cable lowered to the ocean floor.
For long network segments, cable laying may need to be carried out by multiple cable ships. The Auckland-Hawaii leg of the Southern Cross Cable Network, for instance, was laid using three ships during September and October 1999.
The CS Innovator laid 1,371km northeast from Auckland and the CS Nexus 3,306km southwest from Hawaii. The CS Vercors spliced on to the cable end from the Innovator and completed the segment with a 3,318km lay to a final splice position established earlier by the cable laid from the Nexus.
The maximum depth of the cable is 7,585m on the Kermadec Trench between New Zealand and Hawaii.
|